2.3 strictly control the construction quality of external wall tile, doors and windows The construction quality of tile mainly to solve the material the temperature deformation and shrinkage problems solved. Because the decorative brick is brick, dry shrinkage is small on the back of a concave groove is shallow, and its impact on the cement mortar bond strength. The northern face tiles with cement paste paste, due to the pure cement paste shrinkage, affecting the bond force, should use the cement mortar and paste 1:2 as well, in order to increase the bonding force and improve the crack resistance of surfawall plaster machinece layer. Xiangtie should find good rules, according to the actual size of the pop-up brick anyway control line, a number of high level and skin. Joint width should comply with the design requirements, generally about 1~1.5mm. Then according to the thickness of ceramic tile paste nodes with mixed mortar stick ash cake, find out the standard, according to the elastic stability good flat plate, as the first tile mosaic basis. Stick from the corner, from the bottom up layer by layer paste, not into the whole stay in the corner. If there is a pool, pool, should be in the frame, frame as the center to both sides of paste, in short, to put yang angle is large, wiplaster machinery used in indiath negative angle, groove and other difficult position. In the installation of doors and windows before the need to check the hole size, processing the dimension deviation of the wiplastering machine pftndow frame peripheral joints, so as to avoid too large or too small influence of seam quality, the general requirements of frame side and the entrance slit width of about 20mm. The installation must be according to the standard, the horizontal and vertical, fixed, and do a good job of concealed engineering acceptance. After fixing the window frame, the window frame surrounding the polymer waterproof mortar seam, seam to brush a cement waterproofing mortar for mortar, seam to compaction, full, must not have the light phenomenon, check the seam quality prior to the window frame peripheral plastering construction. Cement mortar plaster window set days disk mplaster machine for sale in usaust be drip line. The roughness of cement mortar behind the brick veneer days outside the mouth to mouth lower than. The installation of doors and windows, plaster molding, to productplastering machine usa protection, door and window cannot be destroyed. auto plaster machine and construction equipment management auto plastering machine and construction equipment manufacturer auto plastering machine in uae price and construction equipment manufacturers auto rendering machine and construction equipment names auto rendering machine price and construction equipment news automatic randering machine and construction equipment operator automatic rendering machines and construction equipment parts automatic rendering mechine and construction equipment pictures automatic plaster rendering machine and construction equipment prices automatic plastering machine and construction equipment rental